As data centre power share heads for 21pc, Putrajaya moves to avoid ‘phantom demand’ hogging Malaysia’s grid

KUALA LUMPUR, Nov 4 — Data centre operators seeking grid connection in Peninsular Malaysia must now submit 10-year staggered energy projection plans and execute binding...

Malay MailMalay Mail查看原文 ↗
随着数据中心用电份额逼近21%,布城采取措施避免“幽灵需求”占用马来西亚电网资源。

The Malaysian government has introduced new regulations requiring data center operators in Peninsular Malaysia to submit 10-year energy projection plans and secure binding agreements with Tenaga Nasional Berhad, aiming to curb speculative power capacity hoarding.

The policy necessitates strict evaluations of actual energy consumption and phased grid access, combating "phantom demand" and improving alignment between contracted and real-world usage.

As data center electricity consumption is projected to triple by 2030, the regulations encourage operators to utilize green energy options and develop on-site power sources.

However, details on enforcement and penalties for unmet projections remain unspecified.

KUALA LUMPUR, Nov 4 — Data centre operators seeking grid connection in Peninsular Malaysia must now submit 10-year staggered energy projection plans and execute binding commercial pacts with Tenaga Nasional Berhad (TNB), as the federal government clamps down on speculative developers hoarding power capacity.

The regulatory conditions were detailed in a written parliamentary reply by the Ministry of Energy Transition and Water Transformation to Rompin MP Datuk Abdul Khalib Abdullah, who questioned the mounting electricity and water footprints of hyperscale computing facilities on domestic reserve margins.

Under the framework, grid access approvals now hinge on strict technical evaluations assessing actual load matching and localized transmission capacity. Rather than granting bulk allocations upfront, the government is releasing grid access in phases governed by binding Electricity Supply Agreements (ESA) to eradicate what the ministry termed “phantom demand”, referring to artificial capacity bookings that inflate reserve commitments without translating into operational consumption.

Official data highlights a widening disconnect between contracted grid allocations and real-world utilization. As of August 2026, contracted data centre capacity stood at 2,346 megawatts (MW), yet active facilities were drawing only 1,374 MW, representing 58.6 per cent of contracted volumes.

The discrepancy leaves nearly 970 MW of generation capacity ring-fenced on paper but unused in practice, though the ministry did not distinguish between standard phased facility ramp-ups and purely speculative bookings.

The power clampdown arrives as data centres claim an increasingly dominant share of national energy production. Computing facilities are forecast to triple their electricity consumption from 7 per cent of peninsular demand (10,544 gigawatt-hours) in 2026 to 21 per cent (39,289 Gwh) by 2030.

The ministry gave assurances that this expansion has been integrated into the Peninsular Generation Development Plan, projecting that the regional reserve margin will remain stable between 25 and 27 per cent through 2035 through phased renewable additions, new thermal capacity, and operational life extensions for existing power plants.

To prevent hyperscalers from crowding out domestic consumers on the public grid, the government is urging operators to tap green power through Third Party Access (TPA) under the Corporate Renewable Energy Supply Scheme (CRESS), which allows direct corporate procurement from independent green power producers.

Operators developing mega-scale campuses are also being pushed to incorporate dedicated on-site power generation, including micro gas turbines and industrial rooftop solar installations, to alleviate pressure on national baseload margins.

While the Energy Commission continues to monitor load growth alongside the Ministry of Investment, Trade and Industry’s Data Centre Task Force, the ministerial reply leaves key regulatory enforcement rules unresolved.

The government stopped short of detailing financial penalties for operators whose real-world energy draw falls short of their 10-year projections, or establishing formal mechanisms to claw back and reallocate stranded capacity to competing industrial users.

Malaysia ensures food, water and legal assistance for 130 citizens detained in Pakistan over cyber-scam links

Yuneswaran: Deepavali expo boosts small traders while promoting racial unity through cultural celebrations

Flooding shuts key Shah Alam expressway links, diversions active on NKVE and ELITE

手机左右滑动,电脑按 ← → 键,也能切换新闻