JAKARTA, Oct 13 — Electricity supply has been restored to nearly 99 per cent of affected customers on Indonesia’s Batam and Bintan islands following a massive blackout on...

Malay MailMalay Mail查看原文 ↗
巴淡岛、民丹岛停电后印尼恢复供电,原因仍不明

As of October 13, electricity supply has been restored to nearly 99% of affected customers on Indonesia's Batam and Bintan islands after a significant blackout on Monday, which severely disrupted businesses, communications, and essential services.

State electricity provider PLN Batam reported that 406,083 out of 411,219 customers had power restored, prioritizing vital installations such as airports, hospitals, and ports.

The blackout, which began at 6:30 am on Monday, left several areas without power until late into the night, and investigations into the cause are ongoing.

Additionally, water treatment facilities were also affected, functioning at only 30% of their normal capacity due to limited backup generators.

JAKARTA, Oct 13 — Electricity supply has been restored to nearly 99 per cent of affected customers on Indonesia’s Batam and Bintan islands following a massive blackout on Monday that disrupted businesses, communications and water supply.

State electricity provider PLN Batam said 406,083 of the 411,219 affected customers had regained power as of 4 am Tuesday.

“Restoration is being carried out gradually, with special attention given to electricity supply for vital installations and public service facilities, such as airports, hospitals, ports and other strategic facilities,” it said in a statement posted on social media.

The prolonged outage severely disrupted daily activities, with residents reporting difficulties accessing mobile networks, making digital payments and obtaining basic services.

Some businesses and accommodation facilities were also left without electricity and water supply, while residents and visitors sought refuge at premises equipped with generators.

PLN Batam said the blackout began around 6.30 am on Monday, with partial restoration reported by 8.49 am, although outages persisted in several areas into the night.

It said 496.7 megawatts (MW) of the affected 501.8 MW had been restored, with all 11 substations and 12 transmission units back in operation.

One distribution feeder remained under repair.

The cause of the blackout was still under investigation.

The Batam Development Authority confirmed that the blackout had also affected water treatment facilities, with backup generators capable of supporting only about 30 per cent of normal water production. — Bernama

Indonesia’s Mount Semeru erupts 10 times in 13 hours, triggering warnings over deadly flows

Patients aged 65+ left waiting over 24 hours in Australian emergency departments surge 254pc

‘You cannot denotify the resistance’: India’s Cockroach Janta Party defies crackdown to enter landmark Delhi protest site

MetMalaysia warns of severe storms across peninsula and East Malaysia

Molotov cocktail attack on Kulai Rohingya settlement linked to provocative viral clip, police say

Miri-Subang flights to begin Dec 1, offering new link to Klang Valley

手机左右滑动,电脑按 ← → 键,也能切换新闻