Exclusive-Australian outback data centre pulls timeline after regulator stalls

DARWIN/SYDNEY, Nov 2 (Reuters) - The developer of one ⁠of Australia's biggest planned data centres scrapped its target start date after a regulator said it needed longer than usual to set environmental parameters, a setback to the country's ambitions ⁠to be a fast-track destination for AI investment.

The Star MalaysiaHelen Clark, Byron Kaye查看原文 ↗
独家报道:澳大利亚内陆数据中心因监管机构阻挠而推迟项目进度

FILE PHOTO: FILE PHOTO: The Northern Territory Minister of Mining and Energy Gerard Maley, Tamboran Resources Chief Executive Officer Todd Abbott, Australia's Minister for Resources Madeleine King and Northern Territory Chief Minister Lia Finocchiaro turn on the gas supply to Darwin from the Beetaloo Basin during a ribbon-cutting ceremony at Shenandoah South shale gas project near Daly Waters, Australia, September 1, 2026. REUTERS/Helen Clark/File Photo/File Photo

DARWIN/SYDNEY, Nov 2 (Reuters) - The developer of one ⁠of Australia's biggest planned data centres scrapped its target start date after a regulator said it needed longer than usual to set environmental parameters, a setback to the country's ambitions ⁠to be a fast-track destination for AI investment.

Startup Energy North, which says it has finance lined up for a sprawling gas and solar-powered data centre on a cattle ranch ‌in the country's remote north, 683 km (424 miles) from the nearest city, had given a "first power" date of June 28, 2028, in regulatory filings four months ago.

Thank you for your report!

Copper falls as technology rout and oil surge fuel growth fears

JF Technology proposes two-for-five bonus issue of free warrants

JF Technology in bonus issue of free warrants

手机左右滑动,电脑按 ← → 键,也能切换新闻