RTS Link timeline: From 2010 announcement to 2027 launch targetRTS Link 时间表:从 2010 年公布到 2027 年发布目标
The Johor Bahru-Singapore Rapid Transit System (RTS) Link has been more than 16 years in the making, with the project undergoing several changes, a suspension and revised timelines since it was first announced in 2010.The 4km cross-border rail link will connect Woodlands North in Singapore to Bukit Chagar in Johor Bahru, with the journey expected to take around five minutes....

The Johor Bahru-Singapore Rapid Transit System (RTS) Link has been more than 16 years in the making, with the project undergoing several changes, a suspension and revised timelines since it was first announced in 2010.
The 4km cross-border rail link will connect Woodlands North in Singapore to Bukit Chagar in Johor Bahru, with the journey expected to take around five minutes.
Following RTS Operations' announcement on Oct 2 that passenger service is expected to begin in February 2027, here is a look at the key milestones in the RTS Link's development.
Timeline of RTS Link
May 2010: RTS Link first announced, with a target completion date of 2018.
January 2019: Then Transport Minister Khaw Boon Wan said the project was behind schedule and could be delayed beyond 2024.
April 2019: The project was suspended for six months at Malaysia's request as both sides reviewed its scope, structure and costs.
July 2020: The project was officially resumed. Under the revised plans, the RTS Link would connect Woodlands North in Singapore to Bukit Chagar in Johor Bahru.
March 2023: Piling works for the RTS Link's Singapore section were completed, marking a key construction milestone for the project.
January 2024: Singapore and Malaysia marked the completion of the connecting span across the Straits of Johor, linking the two sides of the RTS Link.
November 2024: More than four-fifths of Singapore's civil infrastructure works had been completed, while Malaysian railway civil infrastructure works had reached 93 per cent completion.
June 2025: The first RTS Link train was unveiled at the Singapore Rail Test Centre. RTSO said rail systems works were around 56 per cent complete.
July 2025: Senior Minister K Shanmugam said the RTS Link was targeted to begin operations at the end of 2026, with preparations well underway.
February 2026: The first RTS Link train arrived at Woodlands North Station for testing.
April 2026: The Cross-Border Railways (Border Control Co-location) Bill was introduced in Parliament, setting out arrangements for co-located immigration, customs and quarantine facilities at both RTS Link stations.
May 2026: The Bill was passed following its Second Reading and wrap-up debate in Parliament.
June 2026: Law and Home Affairs Minister Edwin Tong visited Woodlands North Station as construction and preparations for the new cross-border rail service continued.
September 2026: LTA announced the completion of Woodlands North Station, with its Temporary Occupation Permit obtained.
October 2026: RTSO said all system tests and trial runs are expected to be completed by Dec 31, 2026. Taking into account the expected duration of the remaining works, third-party safety certification and approvals from both grantors, passenger service is currently expected to commence in February 2027.
asyiqin.nadzri@asiaone.com
新山-新加坡快速交通系统(RTS)连接线项目历经16年多的筹备,自2010年首次宣布以来,该项目经历了多次变更、暂停和时间表的修改。
这条4公里长的跨境铁路将连接新加坡兀兰北和柔佛新山武吉查卡,预计全程大约需要5分钟。
继RTS运营公司于10月2日宣布预计将于2027年2月开始提供客运服务之后,以下是RTS Link发展历程中的关键里程碑。
RTS Link 的时间线
2010 年 5 月:RTS Link 项目首次公布,目标完成日期为 2018 年。
2019 年 1 月:时任交通部长许文远表示,该项目进度落后,可能会推迟到 2024 年以后。
2019 年 4 月:应马来西亚的要求,该项目暂停六个月,以便双方审查其范围、结构和成本。
2020年7月:该项目正式恢复。根据修订后的计划,RTS Link将连接新加坡兀兰北站和柔佛新山武吉查卡站。
2023 年 3 月:RTS Link 新加坡段的桩基工程竣工,标志着该项目建设取得了重大进展。
2024 年 1 月:新加坡和马来西亚庆祝了连接柔佛海峡两岸的桥梁竣工,连接了 RTS Link 的两岸。
2024 年 11 月:新加坡超过五分之四的民用基础设施工程已经完成,而马来西亚铁路民用基础设施工程已完成 93%。
2025年6月:首列RTS Link列车在新加坡铁路测试中心亮相。RTSO表示,铁路系统工程已完成约56%。
2025 年 7 月:高级部长尚穆根表示,RTS Link 计划于 2026 年底开始运营,目前各项准备工作正在顺利进行中。
2026 年 2 月:首列 RTS Link 列车抵达兀兰北站进行测试。
2026 年 4 月:《跨境铁路(边境管制合设)法案》提交议会,规定了在 RTS Link 两个车站设立合设的移民、海关和检疫设施的安排。
2026 年 5 月:该法案在议会经过二读和总结辩论后获得通过。
2026 年 6 月:律政兼内政部长唐振辉视察兀兰北站,当时新的跨境铁路服务的建设和准备工作仍在继续。
2026 年 9 月:陆路交通管理局宣布兀兰北站竣工,并已获得临时占用许可证。
2026年10月:RTSO表示,所有系统测试和试运行预计将于2026年12月31日完成。考虑到剩余工程的预计工期、第三方安全认证以及双方拨款方的批准,目前预计客运服务将于2027年2月开始。