Rapid KL to begin Kelana Jaya Line track replacement works on Sept 13

KUALA LUMPUR, Sept 9 — Rapid KL will begin phased track replacement works on the Kelana Jaya Line from Sunday, with affected stations starting services at 9.30am on...

Malay MailMalay Mail查看原文 ↗
Rapid KL将于9月13日开始Kelana Jaya线轨道更换工程

Rapid KL will commence phased track replacement on the Kelana Jaya Line starting Sunday, adjusting service start times at affected stations to 9.30 am instead of 6 am on specified Sundays.

The works, which will take place over seven phases and conclude by September 2027, involve comprehensive track and maintenance updates to enhance infrastructure reliability and safety.

During these periods, ticket machines at impacted stations will be unavailable until 9.30 am, but ticket purchases can still be made at counters, and free shuttle buses will operate to assist passengers.

Rapid KL advises passengers to stay informed about updates via myRapid or Rapid KL's social media platforms.

KUALA LUMPUR, Sept 9 — Rapid KL will begin phased track replacement works on the Kelana Jaya Line from Sunday, with affected stations starting services at 9.30am on designated Sundays instead of the usual 6am.

The works involve replacing existing tracks with new ones, along with related maintenance activities to ensure the line’s infrastructure remains safe and reliable.

The track replacement will be carried out in seven phases and is expected to be fully completed by September 2027.

Rapid KL said areas with long curved track sections require more time for replacement, with works on the specified dates extending into the morning to allow the work to be completed properly.

The affected stations and dates are:

Phase 1: Sept 13, 20 and 27, 2026 — Taman Melati and Gombak

Phase 2: Nov 15, 22 and 29, 2026 — Universiti, Kerinchi and Abdullah Hukum

Phase 3: Jan 10, 17 and 24, 2027 — Dato’ Keramat, Jelatek and Setiawangsa

Phase 4: March 14, 21 and 28, 2027 — Universiti, Kerinchi and Abdullah Hukum

Phase 5: May 9, 16 and 23, 2027 — Masjid Jamek, Dang Wangi, Kampung Baru, KLCC and Ampang Park

Phase 6: July 11, 18 and 25, 2027 — Taman Jaya, Universiti, Kerinchi and Abdullah Hukum

Phase 7: Sept 12, 19 and 26, 2027 — Taman Melati and Gombak

Rapid KL said trains at stations not affected by the track replacement works would operate as usual according to their daily operating schedules.

At affected stations, ticket machines will be temporarily unavailable until 9.30am, although passengers can purchase tickets at station counters. Rapid KL and Touch ‘n Go product users can continue their journeys as usual.

Rapid KL will provide free shuttle buses connecting the affected stations throughout the track replacement works to help passengers continue their journeys.

Station staff, auxiliary police and Prasarana Troopers will also be stationed at the affected and relevant interchange stations to assist passengers.

Signboards and information leaflets will be provided as additional guidance.

Rapid KL advised Kelana Jaya Line passengers, particularly those travelling on the affected Sunday mornings, to check for the latest information on the work schedule, affected stations and alternative services via myRapid or Rapid KL’s official social media channels.

The operator said the track replacement works were necessary to maintain the safety and reliability of the Kelana Jaya Line and support more reliable rail services in the future.

Anwar: Govt to provide assistance, support to families of five killed in Sarawak helicopter crash

Pilot killed in Sarawak helicopter crash had video call with mother for more than an hour before tragedy, says father

Perak steps up preparations for Super El Nino expected to last until early 2027

手机左右滑动,电脑按 ← → 键,也能切换新闻