Audit Dept: LCS project 7.55pc behind schedule, risks handing over ship without full capability

KUALA LUMPUR, Oct 5 — The Littoral Combat Ship (LCS) project was 7.55 per cent behind schedule as of June 25, 2026, with delays ranging from 30 to 108 days, according to the...

Malay MailMalay Mail查看原文 ↗
审计部门:濒海战斗舰项目进度落后7.55%,存在交付能力不完全合格的风险。

The National Audit Department reported that the Littoral Combat Ship (LCS) project is 7.55% behind schedule as of June 2026, causing potential risks to the planned Physical Handover (PHO) of LCS 1.

Delays range from 30 to 108 days, impacting full operational capability due to incomplete training and weapon systems.

The audit emphasizes that the complete operational readiness of the LCS depends on a Supplementary Contract set for December 2035, suggesting a gap beyond the initial Main Contract deadline.

The Auditor General's report recommends urgent recovery plans and enhanced project monitoring by the Ministry of Defence to ensure timely project delivery.

KUALA LUMPUR, Oct 5 — The Littoral Combat Ship (LCS) project was 7.55 per cent behind schedule as of June 25, 2026, with delays ranging from 30 to 108 days, according to the National Audit Department (JAN).

In a statement on the Auditor General’s Report (LKAN) 2/2026, the department said the delay posed a risk to the Physical Handover (PHO) of LCS 1, initially scheduled for Aug 26, 2026, and the revised target of Dec 26, 2026.

“Should the PHO take place on either date, LCS 1 will be handed over without full operational capability, as training and weapon systems have yet to be completed.

“Full operational readiness of the LCS project depends on the Supplementary Contract, which can only be completed in December 2035, well beyond the Main Contract’s deadline of April 25, 2030. The delay in the PHO of LCS 1 will also affect the PHO timelines for LCS 2 through LCS 5,” the statement read.

The Auditor General’s Report (LKAN) 2/2026, covering the Federal Government’s Financial Statements for 2025, the activities of federal ministries and departments, as well as state governments, agencies, ministries and departments and the management of state-owned companies, was tabled in the Dewan Rakyat today.

JAN said an interim audit was conducted to assess the management of the LCS Project, including its physical and financial progress, contract management and payments, based on the terms of the contract and regulations in force.

The audit took into account a recommendation by the Public Accounts Committee in its parliamentary report dated Oct 9, 2023, which urged JAN to audit the LCS Project before the handover of LCS 1 to the Royal Malaysian Navy and table the findings in Parliament.

To ensure the LCS Project is completed and handed over with the required level of operational readiness, JAN recommended that the Ministry of Defence establish a realistic recovery action plan, with all critical activities under the Main Contract and Supplementary Contracts aligned with the LCS PHO schedule.

It also recommended that the Ministry ensure any conditional acceptance of the vessels clearly sets out the contractor’s obligations, completion timelines and responsibilities until the vessels achieve the specified operational capabilities.

It was also recommended that the Ministry of Defence strengthen project monitoring by assigning responsible officers and setting deadlines for resolving each critical issue until the project is completed. — Bernama

* Editor’s note: JAN is the Malay abbreviation for Jabatan Audit Negara (National Audit Department), while LKAN stands for Laporan Ketua Audit Negara (Auditor General’s Report).

Hazy start to the week: Cheras, Putrajaya and Johan Setia among seven areas nationwide with unhealthy air

Govt borrowed less in 2025, but collected just 5pc of RM9.273b in loan arrears, says Audit Dept

Education Minister orders security audit of Yong Peng school after student found dead

手机左右滑动,电脑按 ← → 键,也能切换新闻