JB-Singapore RTS Link service start pushed back to February 2027

KUALA LUMPUR, Oct 2 — Passenger service on the Johor Bahru-Singapore Rapid Transit System (RTS) Link is now expected to begin in February 2027, the Malaysian and Singaporean...

Malay MailMalay Mail查看原文 ↗
新山-新加坡RTS连接线服务开通时间推迟至2027年2月

The commencement of passenger service on the Johor Bahru-Singapore Rapid Transit System (RTS) Link has been postponed to February 2027, as announced by the governments of Malaysia and Singapore.

The delay from the initial January target is due to the need for RTS Operations Pte Ltd (RTSO) to achieve independent safety certification and secure final regulatory approvals.

Infrastructure works in both nations are reportedly nearing completion, with remaining testing and commissioning projected to conclude by December 31, 2026.

Authorities are collaboratively working with RTSO to ensure the project's smooth and safe delivery.

KUALA LUMPUR, Oct 2 — Passenger service on the Johor Bahru-Singapore Rapid Transit System (RTS) Link is now expected to begin in February 2027, the Malaysian and Singaporean governments said today.

In a joint statement, the Land Transport Authority of Singapore (Singapore Grantor) and the Ministry of Transport Malaysia (Malaysia Grantor) said they had been informed by RTS Operations Pte Ltd (RTSO) of the revised timeline.

The service was previously expected to commence in January. The new target is subject to RTSO obtaining independent safety certification for the RTS Link and securing final regulatory approvals.

The grantors said infrastructure works in both countries are substantially complete and on track to support passenger service once the remaining testing and commissioning activities are satisfactorily completed.

“More time is needed for the remaining activities prior to service commencement,” the statement said.

RTSO expects to complete its final system tests and trial runs by Dec 31, 2026. It will then need safety certification from an independent safety assessor.

Authorities from both countries must review the certification and be satisfied with it before they grant approval to begin passenger operations.

The grantors said they will continue working with RTSO to facilitate the “smooth and safe” delivery of the project.

Johor conservation efforts produce about 5,000 turtle hatchlings a year

MCMC, MACC to use AI in fight against corruption and abuse of power

Anwar secures fast-track process for missing Malaysians in Nepal

Department mobilises 153 firefighters, medevac teams and buses to ensure optimum safety during F1

手机左右滑动,电脑按 ← → 键,也能切换新闻