Rapid KL begins rollout of platform safety barriers on Kelana Jaya, Ampang/Sri Petaling LRT lines

KUALA LUMPUR, Sept 26 — Rapid KL has begun installing platform safety barriers at stations on the Kelana Jaya and Ampang/Sri Petaling LRT lines, starting with Putra Heights,...

Malay MailMalay Mail查看原文 ↗
Rapid KL 开始在 Kelana Jaya、Ampang/Sri Petaling 轻轨线路上安装站台安全屏障

Rapid KL has initiated the installation of platform safety barriers on the Kelana Jaya and Ampang/Sri Petaling LRT lines, starting at Putra Heights station, which is 85% complete.

This project, which commenced on August 1, aims to enhance passenger safety and travel experience on the rail network.

Putra Heights, an interchange station, serves as a pilot for evaluating the design and operational aspects before broader implementation.

Although no specific timeline or the number of stations involved in the rollout has been disclosed, Dr. Prodyut Dutt emphasized the project's role in prioritizing passenger safety.

KUALA LUMPUR, Sept 26 — Rapid KL has begun installing platform safety barriers at stations on the Kelana Jaya and Ampang/Sri Petaling LRT lines, starting with Putra Heights, where work is now 85 per cent complete.

In a statement today, Rapid KL said the project is part of efforts to strengthen passenger safety and improve the travel experience across its rail network.

Installation began on August 1, with Putra Heights selected as the first station for the project.

Rapid KL said the station would serve as a reference point for the phased rollout of the barriers to other stations once installation and operational aspects have been tested and refined.

Putra Heights was chosen because it is an interchange station serving both the Kelana Jaya and Ampang/Sri Petaling lines, allowing Rapid KL to assess the design, installation process and operational requirements before expanding the project.

Prasarana Group chief operating officer for strategy and development Dr Prodyut Dutt, who is also acting group president and chief executive officer, said the barriers were among measures being taken to provide a safer environment for passengers.

“Passenger safety has always been our priority. The installation of these platform safety barriers is another proactive measure to strengthen safety at stations, while giving passengers greater confidence when waiting for and boarding trains.

“Implementation at Putra Heights station allows us to ensure that installation and operational aspects are properly refined before the project is expanded to other stations,” he said.

Rapid KL did not say how many stations would ultimately receive the barriers or give a timetable for the wider rollout.

Even unfrozen assets won’t immediately cover Najib’s RM50m house-arrest fine, says son

Malaysia, Kazakhstan should deepen higher education cooperation through five‑pillar knowledge partnership, Zambry says

Fahmi: L. Krishnan shaped Malay cinema’s golden era and national film heritage

手机左右滑动,电脑按 ← → 键,也能切换新闻